I never thought the day would come, but last week Steve the Concrete Man poured the dang floor in the Back Room! If it feels like we’ve been waiting an eternity for this, you’d be right. It’s been 7 months since I started the process to get the permits for this project, and now that I have them, we can finally get this sucker going.

Behold some pictures of this glorious floor and check out the timetable for the rest of the project. At this rate, we might have our second bathroom in by August!

MAY 29: POUR! THAT! FLOOR!

MAY 30: Concrete inspection.

JUNE 3-5: Plumbing re-route and update.

June 1-July 5: Source and order materials.

JULY 5: Framings begins.

July 15: Framing inspection

July 15-19: Electrical and Plumbing Rough-In

July 19: Final Framing inspection

July 22-26: Spray foam insulation and inspection

July 29: SHEETROCK! And finishing work.